The Puerto Plata cable car project is underway: cabins for 55 people and a planned reopening in the first quarter of 2028

The new system will replace the one from 1975, which, according to the Board that manages it, in 2024 alone hauled 112,286 people up the mountain to Loma Isabel de Torres, before its closure

SANTO DOMINGO. – In June 2024, the Puerto Plata cable car cabins stopped on the ground because the system's safety could not be certified, and a little over two years later, this Saturday, October 3, the Dominican government began construction to replace the project inaugurated in 1975, with a budget that is not visible in the records of the Ministry of Public Works, the Presidency, or in the newspaper archives.

The Cable Car Board counted 129,229 people who went up to Loma Isabel de Torres until the time of its closure in 2024, of which 112,286 arrived in the cabins that hung from the cables and 16,943 did so by road.

The figures from the Board of Trustees are included in Resolution 006-2024 of the National Institute of Transit and Land Transportation (INTRANT), dated July 2, 2024, and averaged 864 visitors per day. In an interview published years ago by El Caribe, the cable car director stated its capacity at 1,200 people per day.

What happened on October 3rd

The event was led by the Minister of the Presidency, José Ignacio Paliza, and the work is being carried out by the Unit for the Readaptation of Neighborhoods and Environments (URBE) and the DOMA Consortium, formed by the Austrian Doppelmayr Seilbahnen GmbH and the Dominican construction company Grupo Malespín, which will be in charge of replacing the original system with a double-cable swing cable car with two panoramic cabins of 55 passengers each, compared to the 18 or 20 that fit in the previous ones, increasing its capacity to up to 430 passengers per hour in each direction.

Luz Elena Lugo Alarcón, representative of Doppelmayr, specified that the journey will take between five and six minutes, two to three less than the eight of the previous route, and that the project includes the adaptation of the lower and upper stations and a new intermediate base, in galvanized steel.

The launch is planned for the first quarter of 2028.

The official statement does not mention the amount of the work, although El Nacional places it at around 22 million dollars, and the international tender had a base of 1,280 million pesos.

The funds come from the Ministry of Tourism and the Dominican Institute of Civil Aviation (IDAC), whose director general, Igor Rodríguez, reported that his institution contributed 6 million dollars, from its own savings, to start the work, and affirmed that the new system will meet the highest standards of safety and reliability.

Paliza maintained that the modernization “combines the historical value it holds for this province” with a safer, more accessible, and higher-capacity infrastructure. When presenting the project months earlier, he had described the cable car as “a symbol of Dominican tourism” for five decades.

A path and a Christ at the top

According to the cable car's own timeline, the Christ the Redeemer statue was installed atop the hill in 1970, and in June 1971 construction began on the El Cupey road, opened to allow machinery and equipment to ascend. It was architect Cristian Martínez who proposed the idea for a funicular, and the president at the time, Joaquín Balaguer, ordered the work to begin.

In 1972, civil works began, with equipment supplied and installed by the Italian firm Ceretti e Tanfani, and in 1973, engineer Benjamín Paiewonsky was commissioned to convert the summit into a botanical garden.

At the end of 1974 the equipment was assembled and six months of testing followed, and finally, on July 19, 1975, the cable car opened to the public, after four years and one month between the construction of the road and three years of civil works.

During its time in service, the cable car, which became part of Puerto Plata's complementary tourist offerings, had glass cabins for 18 or 20 passengers for an eight-minute ride. It was managed by the Ministry of Public Works, the Botanical Garden, and the Ministry of Tourism until 2000, when the government created a board of trustees to manage it, comprised of six institutions and four prominent figures from Puerto Plata.

Tourism authorities in the province estimated that a high percentage of foreign visitors arriving on cruise ships used it, according to press reports.

The 1975 work, without a public figure

None of the public sources consulted, including the National Archives, provide the construction cost of the original cable car. No amount is listed for the contract with Ceretti e Tanfani, nor for the El Cupey road, opened in June 1971, nor for the gardens from 1973.

The project was built in stages: the road, the civil works, overseen by the Ministry of Public Works and the Presidential Office for the Technical Auditing of Works and Investments, the supply and installation of equipment, and the summit transformed into a garden. The money spent on this phase left no public trace.

The contrast with today's project is one of two eras. The current construction project went out to international tender, received two bids, and was awarded for approximately $22 million, based on a budget of 1.28 billion pesos. All that is known about the 1975 project is who conceived it, who ordered its construction, and which Italian firm supplied the equipment.

Balaguer already has his place in the history of the cable car, and a legislative initiative seeks to give him another, in its name. A bill introduced by Senator Ginette Bournigal proposes naming it the Puerto Plata Cable Car "Dr. Joaquín Balaguer" and mandates placing his name in bronze on a plaque with biographical information about the former president and the construction date. The Senate approved it on second reading in 2021, amidst dozens of criticisms, and the full Senate approved the bill on March 31, 2022.

The start of construction reignited the debate, as engineer Miguel Jiménez Messón, the senator's husband and former Secretary of State for Public Works in Balaguer's governments, maintained that the president showed a particular interest in the cable car while it was being built, and revealed that Bournigal also proposes a plaque at the base for engineer Gilberto Pagán, whom he credits with the execution of the project.

Myrna Santos, widow of Amín Abel Hasbún, had already questioned the recognition due to the human rights violations associated with the Twelve Years.

In official communications this week, the system continues to be called the Puerto Plata Cable Car.

Impact on those who live off the top

On May 23, 2024, according to Listín Diario, a pulley malfunction left 32 people stranded for hours. After service resumed, the company advising on the operation certified it and later recommended its closure. The closure was ordered in early June, when technical studies concluded that the system's safety could not be certified.

Since then, taxi drivers, guides, artisans, vendors, and restaurant owners at the top have seen their incomes plummet. Merchants estimate accumulated losses of over 500 million pesos, and El Nacional reports that some 200 families depend, directly or indirectly, on the cable car's operations.

In December 2025, 18 months after the closure, vendors and transporters held a "symbolic inauguration" and reminded everyone that the project should be completed within that timeframe.

Robinson Rodríguez, a leader of the merchants, said at the time that they had not received a response to their demands and that people who live off that work "have gotten sick, have had to sell properties" after losing their income.

The vendors also disputed the estimate: they maintained that the government valued the project at $64 million, a figure that, according to Arecoa, corresponded to a project of the Trust for the Mass Transit System (FITRAM) and was deemed impossible to execute, while they had obtained quotes directly from the same company and received a budget of $22 million. In the end, the contract was awarded for a price close to that second figure.

For those who live off the top, the count is not marked by the official date but by the calendar: 27 months of closure.

Recommended readings:

Be the first to know about the most exclusive news

Advertisingspot_img
Solangel Valdez
Solangel Valdez
Journalist, photographer, and public relations specialist. Aspiring writer, reader, cook, and wanderer.
Related Articles
Advertising Banner Coral Golf Resort SIMA 2025
Advertising
Advertising spot_img